Feasibility
Define the selected option fully so the board can make the final investment decision.
Key activities
- Basic engineering: P&IDs, GAs, 3D model to about 30%
- Equipment specifications, RFQs and vendor budget quotes
- MEL, EEL, instrument index and line list
- HAZOP on P&IDs, constructability reviews
- Execution plan, contracting and procurement strategy
- Environmental authorisation, water use licence and mining right applications
- Quantitative cost and schedule risk analysis
Key deliverables
- Approved design criteria and specifications
- P&IDs issued for design
- GA drawings and 3D model
- Priced MEL and EEL
- Drawing register (MDR)
- Class 3 estimate and basis of estimate
- Level 3 schedule and basis of schedule
- Project execution plan
- Feasibility study report
Mining scope Open pit
- Detailed pit design and life-of-mine schedule
- Waste dump, stockpile and haul road design
- Pit dewatering design
- Mining contract or fleet purchase strategy
Project controls
- Semi-detailed estimate from MTOs and vendor quotes
- Integrated Level 3 schedule with agreed critical path
- Cost and schedule QRA, P50 and P80 contingency
- Control budget structure and earned value set-up
Exit gate
Is the defined project fundable and executable within the approved cost, schedule and risk?
- Deliverables at Class 3 maturity
- Contingency set at the board's chosen P-level
- Critical permits granted or on a clear path
- Funding secured, execution team ready
- Estimate
- Class 3
- Accuracy
- -10 to -20% / +10 to +30%
- Defined
- 10 to 40%
- Schedule
- Level 3