Mine Delivery Roadmap

How a large mining project, greenfields or brownfields, moves from business need to a delivered business case. Five views cover the phases and gates, how objectives become packages of work, how engineering matures, and how it turns into an estimate fit for each gate.

Select a phase to see its activities, deliverables and exit gate. Switch between greenfields and brownfields, and between open pit and underground, to change the content throughout. Gate names, maturity levels and examples are typical of industry practice; align them to your own stage-gate framework.

Lifecycle roadmap

Eight phases from business need to business case delivery. Each phase ends at a gate where the owner decides to proceed, recycle or stop. Select a phase to see what happens in it.

Define
Front-end loading (studies)
Execute
Operate
Phase
Stage
Opportunity
FEL 1 / Scoping
FEL 2 / PFS
FEL 3 / FS
EPCM delivery
Handover
Operations
Operations
Estimate class
No class
Class 5
Class 4
Class 3
Class 2, then Class 1
Final cost report
Operating budget
Post-investment review
Accuracy range
Benchmark only
-20 to -50% / +30 to +100%
-15 to -30% / +20 to +50%
-10 to -20% / +10 to +30%
-5 to -15% / +5 to +20%
Actuals
Actuals
Actuals
Engineering defined
n/a
0 to 2%
1 to 15%
10 to 40%
30 to 100%
100%
n/a
n/a
Schedule level
Milestones
Level 1
Level 2
Level 3
Level 4 and 5
By system
Ramp-up curve
Life-of-mine plan
Resource status
Exploration results
Inferred and Indicated
Probable Reserve declarable
Proved and Probable
Grade control model
Reconciliation starts
Mine-to-mill reconciliation
Annual reserve update
Exit gate
G0Opportunity framed
G1Concept selected for PFS
G2Preferred option selected
G3Final investment decision
G4Ready for commissioning
G5Handover to Operations
G6Nameplate demonstrated
G7Business case confirmed
Phase 04 of 08 . FEL 3 / FS . Greenfields

Feasibility

Define the selected option fully so the board can make the final investment decision.

Key activities

  • Basic engineering: P&IDs, GAs, 3D model to about 30%
  • Equipment specifications, RFQs and vendor budget quotes
  • MEL, EEL, instrument index and line list
  • HAZOP on P&IDs, constructability reviews
  • Execution plan, contracting and procurement strategy
  • Environmental authorisation, water use licence and mining right applications
  • Quantitative cost and schedule risk analysis

Key deliverables

  • Approved design criteria and specifications
  • P&IDs issued for design
  • GA drawings and 3D model
  • Priced MEL and EEL
  • Drawing register (MDR)
  • Class 3 estimate and basis of estimate
  • Level 3 schedule and basis of schedule
  • Project execution plan
  • Feasibility study report

Mining scope Open pit

  • Detailed pit design and life-of-mine schedule
  • Waste dump, stockpile and haul road design
  • Pit dewatering design
  • Mining contract or fleet purchase strategy

Project controls

  • Semi-detailed estimate from MTOs and vendor quotes
  • Integrated Level 3 schedule with agreed critical path
  • Cost and schedule QRA, P50 and P80 contingency
  • Control budget structure and earned value set-up

Exit gate

G3 Final investment decision

Is the defined project fundable and executable within the approved cost, schedule and risk?

  • Deliverables at Class 3 maturity
  • Contingency set at the board's chosen P-level
  • Critical permits granted or on a clear path
  • Funding secured, execution team ready
Estimate
Class 3
Accuracy
-10 to -20% / +10 to +30%
Defined
10 to 40%
Schedule
Level 3

Accuracy ranges show the low and high bounds of the AACE range for that class; the actual range depends on technology, complexity and data quality. Mining studies are often quoted more simply: scoping about +/-35 to 50%, PFS about +/-25%, FS about +/-10 to 15%.

Estimate classes and accuracy ranges follow AACE International RP 47R-11 (mining and mineral processing) and 18R-97. Reserve terms follow the SAMREC Code (2016).